| Project Title |
Construction of Six Lane access-controlled Highway from Junction with Jaitpur - Pushta Road to Junction with Sector-62/65 dividing road on Faridabad – Ballabhgarh Bypass Section of NH-148NA (Design Ch. 9+000 to 33+000) including spur from Design Ch. 13+200 to Junction of Faridabad - Ballabhgarh Bypass with NH-19 near Badarpur Border in the state of Haryana on Hybrid Annuity Mode under Bharatmala Pariyojana Pkg-II. |
| Employer |
"National Highways Authority of India, Plot No.G-5 & G- 6, Sector – 10, Dwarka, New Delhi – 110 075." |
| Concessionaire |
Dineshchandra Vaishnodevi Infra Private Limited |
| Independent Engineer |
Intercontinental Consultants and Technocrats Pvt. Ltd. |
| Total Project Length |
24.00 Km |
| Contract value |
Rs. 1729.00 crores |
| Letter of Award Date |
30th July 2020 |
| Concession agreement signed |
21st October 2020 |
| Appointed Date |
10 August 2021 |
| Schedule completion Date |
730 days from Appointed date (10/08/2023) |