Salient Features

Salient Features

Particulars Details/Status
Project Title Construction of Six Lane access-controlled Highway from Junction with Jaitpur - Pushta Road to Junction with Sector-62/65 dividing road on Faridabad – Ballabhgarh Bypass Section of NH-148NA (Design Ch. 9+000 to 33+000) including spur from Design Ch. 13+200 to Junction of Faridabad - Ballabhgarh Bypass with NH-19 near Badarpur Border in the state of Haryana on Hybrid Annuity Mode under Bharatmala Pariyojana Pkg-II.
Employer "National Highways Authority of India, Plot No.G-5 & G- 6, Sector – 10, Dwarka, New Delhi – 110 075."
Concessionaire Dineshchandra Vaishnodevi Infra Private Limited
Independent Engineer Intercontinental Consultants and Technocrats Pvt. Ltd.
Total Project Length 24.00 Km
Contract value Rs. 1729.00 crores
Letter of Award Date 30th July 2020
Concession agreement signed 21st October 2020
Appointed Date 10 August 2021
Schedule completion Date 730 days from Appointed date (10/08/2023)
Particulars Details/Status
Minor Bridge 03 Nos.
Elevated Structure 5 Nos.
Flyover 8 Nos.
LVUP 01 Nos.
Vehicular Underpass 02 Nos.
Box Culverts 27 Nos.
Box Culverts for Connecting Road 19 Nos.
"Additional Box Culverts for Connecting Road" 16 Nos.
Service/Slip Road 47.00 Km
RE Wall 148610 Sqm
Road Side Drain 45.986 Km
Loops/Ramps/Spur 01 Nos.
Bus Shelters 25 Nos.
Entry/Exit Location 08 Nos.
Existing Carriageway 6-Lane
Proposed Carriageway 6-Lane (28.5 mtr.)+Service Road
Total Project Length 24.00 Km.
Elevated Section Length 4.336 Km